Adult Steelhead Query Parameters | |
Year | 2016 |
Project | John Day |
River Parameter | Tailrace TDG Percent |
Critical Tailrace TDG Percent Value | 115 % |
Calculate Exposure | Above Critical Value |
River Parameter Data Fill | No |
Query Dates | 1/1 - 12/31 |
Total Run Period (Apr 1 - Oct 31) | |
Total Number of Fish Observed | 130626 |
Percent of Total Run Analyzed [Number Observed] | 100 % [130626] |
Tailrace TDG Percent Exposure Index | 101.97 % |
Percent of Fish Exposed [Number Exposed] | 0.1 % [245] |
Number of Days Fish Exposed | 37 |
Middle 80% of Run Period (Jul 31 - Oct 9) | |
Number of Fish Observed | 105482 |
Percent of Middle 80% of Run Analyzed [Number Observed] | 100 % [105482] |
Tailrace TDG Percent Exposure Index | 100.85 % |
Percent of Fish Exposed [Number Exposed] | 0 % [0] |
Number of Days Fish Exposed | 0 |
Middle 50% of Run Period (Sep 9 - Sep 29) | |
Number of Fish Observed | 68226 |
Percent of Middle 50% of Run Analyzed [Number Observed] | 100 % [68226] |
Tailrace TDG Percent Exposure Index | 99.75 % |
Percent of Fish Exposed [Number Exposed] | 0 % [0] |
Number of Days Fish Exposed | 0 |
Run Dates | |
First Day of Run | Apr 1 |
5% of Run passed | Jul 12 |
10% of Run passed | Jul 31 |
50% of Run passed | Sep 19 |
90% of Run passed | Oct 9 |
95% of Run passed | Oct 14 |
Last Day of Run | Oct 31 |
Date(s) When Tailrace TDG Percent Crosses 115 % | |
Apr 14, May 14, May 16, May 18, May 20, May 22, May 24, May 26, Jun 5, Jun 7, Jun 8, Jun 10 |