PIT-Tagged Wild Spring/Summer Chinook Query Parameters | |
Year | 2019 |
Project | Little Goose |
River Parameter | Temperature |
Critical Temperature Value | 15 C |
Calculate Exposure | Above Critical Value |
River Parameter Data Fill | No |
Query Dates | 1/1 - 12/31 |
Total Run Period (Mar 26 - Jul 29) | |
Total Number of Fish Observed | 5652 |
Percent of Total Run Analyzed [Number Observed] | 100 % [5652] |
Temperature Exposure Index | 10.58 C |
Percent of Fish Exposed [Number Exposed] | 0.1 % [10] |
Number of Days Fish Exposed | 8 |
Middle 80% of Run Period (Apr 15 - May 18) | |
Number of Fish Observed | 4593 |
Percent of Middle 80% of Run Analyzed [Number Observed] | 100 % [4593] |
Temperature Exposure Index | 10.62 C |
Percent of Fish Exposed [Number Exposed] | 0 % [0] |
Number of Days Fish Exposed | 0 |
Middle 50% of Run Period (Apr 21 - May 8) | |
Number of Fish Observed | 2877 |
Percent of Middle 50% of Run Analyzed [Number Observed] | 100 % [2877] |
Temperature Exposure Index | 10.44 C |
Percent of Fish Exposed [Number Exposed] | 0 % [0] |
Number of Days Fish Exposed | 0 |
Run Dates | |
First Day of Run | Mar 26 |
5% of Run passed | Apr 12 |
10% of Run passed | Apr 15 |
50% of Run passed | Apr 27 |
90% of Run passed | May 18 |
95% of Run passed | May 22 |
Last Day of Run | Jul 29 |
Date(s) When Temperature Crosses 15 C | |
Jun 13 |